Project Overview
Built in 1973, the 5-story, 246-bed hospital was a landmark in Southwest Detroit. After nearly two decades of vacancy, deterioration, and blight, Adamo was selected to safely remove the compromised structure and prepare the 7-acre site for new development. The demolition was completed on schedule and under budget within a 3-month timeline while prioritizing safety, environmental responsibility, and minimal impact to the surrounding community.
Project Details
Owner
Detroit City FC
Project Start
January 1, 2026
Completed
April 1, 2026
Project Value
$389,500