MGM Grand Detroit Casino – Demolition of Michigan Bell Telephone

Adamo demolished the former 200,000 square foot, three-story Ameritech Building meeting an aggressive three week schedule. The work was carried out in restricted space and included the removal of a four foot thick concrete foundation mat 15’ below grade.

A fleet of 14 pieces of equipment working 24 hours per day, 7 days per week removed 32,000 cubic feet of concrete for recycling. The project was completed in 14 days, one week ahead of schedule.